Alright, to answer my own question, I should wait...
I want to participate in the test, please help me to open Invoice #1396917
The beta test is closed for new deployments.
--
Node TYOC039 is in beta testing and reboots and other issues may still happen. Some time needs to go by before the node is considered stable. Node 40 should get redeployed once the problems are worked out. VirMach had mentioned ordering some new NVMe drives, but has not stated an expected date that this node will be redeployed.
I miss the test coz I read all the new posts, that spent me much time, otherwise I would not miss the test. Sometimes people who follow the rules suffer instead, that's how ironic
@fat32 is Singaporean I think.
1366963541
802214
Please open it for me. I also want to participate in this test. Thank you, boss
Almalinux Template is good
invoice#1396816
It seems to be overdue, but I'd like to try a little harder.
The beta test is closed for new deployments.
I want to try it, thanks!
Invoice #1398018
f> @ito said:
I'll let you know by Sunday, thanks for the offer to help. The current ordered ones will arrive tomorrow and if there's issues then I'll need these.
Tokyo Update
Testing is going well so far for the Mushkin Gen4 after kernel parameter updates. These will be used as the third drive so even if they have issues, we're getting new NVMe SSDs in Tokyo right now, arriving tomorrow.
All servers and parts should arrive to where we can deploy all services on Monday or Tuesday. If further compatibility issues occur then at least some of these will be usable to some degree initially and most will still be deployed.
Tokyo is being switched from 10G to 40G sometime next week. Right now these are on 1G because of a compatibility issue with the transceiver on the switch. The switch cannot support 10G as intended, and has to go with 40G only (this is my fault for not looking into the specific compatibility for that specific switch.) We're also getting in a second switch soon for 10G storage node as the current switch cannot output 10G either, only 40G and 1G, it doesn't support 40G to 4 x 10G on this specific model.
San Jose Update
Most other servers are being set up/configured now. This will allow for maximum capacity here soon and migrations will be resumed. Two servers are having some issues, and they're scheduled for maintenance now. All other nodes have no issues.
Dallas Update
Nodes are being configured now as well for this location.
My order hasn't been activated for 3 weeks #1397375
Amsterdam Update
UPS finally responded here, barring further issues which is very possible, these are sending out as soon as they pick it up. They've been ready for some time.
does this mean we shouldn't get horny excited?
First rule of VirMach pre-orders is to keep everything inside your pants until it gets provisioned.
Milestone
Go sleep and wake up repair VPS as soon as possible,Thanks
hahha
Any plan or timeline for internal networking?
@VirMach waiting for 8gb tokyo
Could be, but after deploy all the pending and migration.
so toyko gonna get 40gbps?
It sure sounded like VirMach said that.
6TB on a 40gb/s uplink in Tokyo for >$22/year sounds pretty bad ass.
Please temper your expectations. Most likely their mobos on each server have something like 2x1G ports or 2x10G ports or some config similar to that. I don't think they will buy network adapters at this point to have 40G ports. But the upgrade to overall capacity should still be a good thing.
No worries, my expectation is there could be a 40gb/s uplink for the cab, not my single VPS.
Yep, 40G uplink to the cabinet in Tokyo. Not that it will ever actually get used without bankrupting us.